METRO UNDER CONSTRUCTION!

METRO UNDER CONSTRUCTION!


FINAL STATUS OF THE PROJECT:

  • The construction of Gebze-Darıca Metro was contracted by Kocaeli Metropolitan Municipality on 18/05/2018 and the contract was signed with the Contractor on 12/06/2018.
  • Approximately 2% progress was achieved within the scope of the project and Kocaeli Metropolitan Municipality requested that the project be undertaken by our Ministry.
  • With the President's Decision No. 2019/1550 dated 17/09/2019 regarding the transfer of the said project to our Ministry, the construction of the Project was undertaken by our Ministry.
  • Regarding the transfer of the project to our Ministry, a transfer protocol was signed between Kocaeli Metropolitan Municipality and our Ministry on 18/10/2019 and a transfer agreement was signed with the Contractor on 12/12/2019. The total physical progress made to date after the transfer agreement is 76%.
  • On July 22, 2020, a procurement tender for 28 vehicles was held and the contract was signed on November 4, 2020. The condition of 60% domestic production was sought for the trains and they will be designed in accordance with modern technology, fully driverless at the GoA-4 level.

PROJECT DETAILS

Contract Price

2,488,489,457 TRY

Line Length

2x15.4 Km (30.8 Km)

Number of Stations

11 stations

Design Speed

90 km/hour

Number of Vehicles

4 sets x 7 vehicles = 28 vehicles

Passenger Capacity

330,000 passengers/day

Number of TBMs

2

Tunnel Excavation Amount (NATM+TBM)

1,323,000 m³

Open Excavation Amount

1,871,000 m³

Concrete Amount

1,126,651 m³

Rail Quantity

78,922 mt

* Total Project Progress is 63%.

TECHNICAL INFORMATION
GALLERY
Call Center

ALO 123

© 2022 Ministry of Transport All rights reserved.